Norwegian gas-transport operator Gassco extended Heidrun’s 5.5-million-cubic-meter-per-day supply outage through October 5, from the previously scheduled October 4.

· ComputeLabs Research · from the October 3, 2026 edition

Gassco revised the reported outage window at the Heidrun field (海德伦气田). The original window ran from September 29 through October 4; the revised window runs from September 29 through October 5.

The affected supply figure remains 5.5 million cubic meters per day. This is a daily natural-gas supply quantity associated with the outage, not a cumulative lost volume or an electricity-generation capacity figure.

The update changes the scheduled end date rather than confirming a restart. The supplied message gives no outage cause, repair detail, customer allocation, or quantified effect on gas prices or power markets.