Regional grid operator PJM Interconnection removed Oklo’s 750-megawatt mixed-technology project from its study cycle; Oklo requested federal reinstatement.

PJM Interconnection removed Oklo’s 750-megawatt mixed-technology project from the regional transmission organization’s interconnection-study cycle. An interconnection study evaluates a project’s ability to connect to the grid; removal is not the same as cancellation of an operating plant because the project had not reached that stage.

Read the full story · 1 source →