Malkang Dazang Solar Project (马尔康大藏光伏项目) achieved full-capacity grid connection and entered comprehensive commercial operation.

· ComputeLabs Research · from the September 6, 2026 edition

The Malkang Dazang Solar Project (马尔康大藏光伏项目) completed full-capacity grid connection after its final photovoltaic array was connected and placed into operation. The update was attributed to PowerChina’s official account.

PowerChina served as the project’s general contractor. Following the final connection, the project formally moved into the full production and operating stage.

The source confirms grid connection of the project’s entire planned generating capacity rather than completion of only an individual array or construction package. It does not provide the project’s megawatt capacity, investment cost, location details beyond its name or expected annual generation.

No power-purchase agreement, electricity price, storage configuration or transmission arrangement was disclosed in the cited message. The reported milestone is therefore limited to full-capacity grid connection and the transition to operations.

Additional reporting

All 17 stories from September 6, 2026