China Datang’s Chaozhou Unit 5, a 1,000 MW generating unit, entered commercial operation after 168 hours of full-load trial operation.

· ComputeLabs Research · from the November 28, 2026 edition

According to China Datang, Chaozhou Power Generation Company’s Unit 5 completed its 168-hour full-load trial on November 28. The unit was then formally transferred to production and entered commercial operation.

Unit 5 belongs to the company’s third-phase expansion, which comprises two 1,000-megawatt generating units. The announcement confirms commissioning of Unit 5 specifically, not commercial operation of both units in the expansion.

China Datang reported that the unit’s main and auxiliary equipment operated satisfactorily during the trial. It also said environmental indicators were better than national ultra-low-emission standards and that all performance indicators met design requirements, without supplying individual measurements.