The Zhaoqing Langjiang pumped-storage project completed its water-conveyance system; its first two generating units target commissioning before year-end.
· ComputeLabs Research · from the November 25, 2026 edition
A CCTV report relayed by Financial_Express says the Zhaoqing Langjiang pumped-storage station successfully completed initial water filling, marking completion of its water-conveyance system. China Southern Power Grid described it as the Guangdong–Hong Kong–Macao Greater Bay Area’s first variable-speed pumped-storage project.
The filling test lasted 15 days, placing 210,000 cubic meters of water in the conveyance system. The completed connection links the upper and lower reservoirs with the generating equipment across an elevation difference of 546 meters and a length of nearly 2,800 meters.
The report states that the station can convert the water energy associated with 1.12 million cubic meters per hour into 1.2 million kilowatt-hours of electricity per hour. These are stated operating-capability figures, not measured commercial-generation results supplied for the day.
The first two generating units are expected to enter operation before year-end, with the report citing an addition of 1.2 million kilowatts of grid-regulation capability. Commissioning remains a target: the completed milestone is the water-conveyance system, after which the project entered its final preparation stage.