PowerBank’s estimated $10 million project targets fiscal 2028 operation, pending zoning, permits, and financing; no tenant agreement has been signed.
· ComputeLabs Research · from the November 25, 2026 edition
PowerBank estimates the Ontario facility’s capital cost at approximately $10 million, to be funded by the company and its partner. The supplied excerpt uses an unqualified dollar symbol for this estimate, so it does not establish the currency or each partner’s funding share.
Commercial operation is targeted for fiscal 2028, subject to zoning, a building permit, and financing. No tenant agreement has been signed, and the filed press release establishes that management disclosed these plans—not that funding, occupancy, or the operating date is secured.
Separately, PowerBank disclosed completion of a $25.4 million project-level refinancing on October 26, covering 53 operating solar projects and consolidating 50 credit agreements into one Canadian-bank facility. It reported an approximately $4.2 million, or 14%, reduction in outstanding project loan principal, expected approximately $5 million in net cash subject to post-closing adjustments, and plans to bring maintenance of 49 projects in-house; it did not designate that cash as committed data-center funding.
The filing warns about data-center demand, technology change, established competitors, and securing commercially viable tenants. It also identifies dilution from future securities financings, but supplies no project-specific equity issuance, conversion terms, collateral package, or quantified dilution.