The Federal Energy Regulatory Commission approved faster interconnection studies for the Midcontinent Independent System Operator’s 125 GW generation-and-storage queue.

· ComputeLabs Research · from the November 23, 2026 edition

The Federal Energy Regulatory Commission (FERC) approved the Midcontinent Independent System Operator’s (MISO) plan to accelerate its legacy interconnection-study process. The action concerns how queued projects are studied, rather than confirmation that those projects have been connected.

The affected queue cycles total approximately 125 gigawatts (GW) of generation and storage, according to Utility Dive’s excerpt. That figure is not data-center electrical demand, installed computing capacity, or storage energy measured in gigawatt-hours.

MISO said the queue cycles would otherwise have faced delays without the rule changes. The supplied excerpt does not quantify the time saved, identify the individual projects, or provide their construction and energization dates.