Construction began on the Benzilan hydropower station, the upper Jinsha River’s largest hydropower project by installed capacity.
· ComputeLabs Research · from the November 21, 2026 edition
PowerChina announced that construction had formally begun on the Benzilan hydropower station, which spans Sichuan and Yunnan. The company described it as the largest hydropower station by installed capacity on the upper Jinsha River, rather than across the entire river system.
Benzilan is the 13th cascade station in the upper Jinsha development scheme described as “one reservoir and thirteen stages.” It is also identified as a priority project under China’s 14th Five-Year plans for the modern energy system and renewable-energy development.
PowerChina’s Zhongnan Engineering Corporation is responsible for full-process surveying and design, while Sinohydro Bureau 14 is undertaking construction. The supplied report does not state an installed-capacity figure, construction cost, annual generation estimate, commissioning date, or dedicated AI-infrastructure power contract.