Hyperscale Data’s Form 10-Q states that Bitcoin-mining operations at its Michigan data center ceased effective September 1, 2026. The stated purpose was to make electrical capacity available for deployments by the customer covered by its AI compute, neocloud, and colocation agreement.

This is an operational change disclosed in the filing, separate from the customer agreement itself. The extract does not quantify the electrical capacity released or specify how much had already been occupied by AI equipment.

The transition led to a $2.3 million second-quarter impairment of certain mining equipment, with no additional related charge in the third quarter. The company initially classified the affected assets as held and used while evaluating their future deployment or disposition.

The filing says estimated fair value relied on comparable mining-equipment sales and listings, taking account of model, hash rate, and condition. It attributes the write-down to the change in intended use, rather than physical damage to the equipment.