Grid operator PJM Interconnection submitted a proposal to combine interconnection studies, targeting assessment times of 12 months, down from two years.
· ComputeLabs Research · from the November 16, 2026 edition
PJM said it was submitting a plan to the Federal Energy Regulatory Commission (FERC) to accelerate interconnection processes for power plants and large electricity users such as data centers. The supplied Telegram report describes PJM’s footprint as covering 13 states in the Mid-Atlantic and Midwest.
The proposal would combine feasibility-study processes involving generation, transmission, and large-load interconnections. PJM’s stated target is to shorten the required assessments from two years to 12 months.
This is a proposed assessment timetable, not evidence that projects are already connecting within a year or that total construction schedules have been reduced. The report also says data-center companies could bear a larger share of grid costs under the proposal, but supplies no final allocation formula or approval decision.
Additional reporting
- PJM Interconnection