ComputeLabs Research
GPU-cloud provider WhiteFiber signed a 59-month Sydney service order for approximately 1,200 NVIDIA B300 GPUs, targeting Q1 2027 commencement.
· ComputeLabs Research · from the November 12, 2026 edition
Bit Digital’s quarterly filing discloses that WhiteFiber entered into a master service agreement and initial service order with a technology customer in September 2026. The deployment uses approximately 1,200 NVIDIA B300 GPUs at a third-party data center in Sydney, Australia; this is a GPU count, not a server or rack count.
The initial service order has a 59-month term. Service is expected to commence in Q1 2027, following equipment delivery and customer acceptance, rather than having already begun when the order was signed.
The customer has made a prepayment equal to 12 months of service fees. If service does not begin by the contractual long-stop date, the customer may terminate the order and obtain a refund; the supplied excerpt does not state that deadline, the prepayment’s dollar amount, or total contract value.
The filing separately describes a five-year Paris-region deployment also expected to start in Q1 2027, backed by received customer prepayments and a binding financing term sheet whose definitive documentation remained under negotiation. Those financing disclosures apply to the France project and are not disclosed as financing for Sydney.
- WhiteFiber
- Q1 2027