Zaporizhzhia Nuclear Power Plant restored external electricity through its 330-kilovolt Ferroalloy-1 line, returning plant systems to normal operating mode.

· ComputeLabs Research · from the September 7, 2026 edition

Zaporizhzhia Nuclear Power Plant announced on September 7 that external electricity supply had been restored through the 330-kilovolt Ferroalloy-1 (铁合金-1) line. The supplied reports attribute the update to the plant’s official communication.

Following reconnection, the plant’s systems switched back to normal operating mode. The 330-kilovolt figure identifies the line’s voltage, not its delivered power or the plant’s generation capacity.

The more detailed report says repairs were completed after a new ceasefire arrangement took effect on September 5. The update concerns restoration of incoming electricity and plant-system operation; it does not report reactor restarts or resumed electricity exports.

  • Zaporizhzhia Nuclear Power Plant

All 17 stories from September 7, 2026